csv2journal Milestone 1 Build Plan #
The route. DESIGN_M1.md is the destination and is authoritative for which module owns which requirement; PROCESS.md governs how the work is done.
Each task had a file in docs/tasks/ carrying its own status, and every one of the 181
requirement IDs appeared in exactly one task. Those files were removed once the milestone
closed: everything in them had been absorbed into the tests, the code and DESIGN_M1.md, and what
remained read like a live specification while being a finished plan. The table below is kept as the
record of the order the work was done in. jj history has the files if they are ever wanted.
Tasks are sized to be reviewable in one sitting (PROCESS.md §1). No task closes a whole subsystem.
Order #
| # | Task | Closes | Depends |
|---|---|---|---|
| T01 | packaging skeleton | 6 | — |
| T02 | diagnostics | 4 | T01 |
| T03 | decimal | 4 | T02 |
| T04 | yaml event layer | 8 | T02 |
| T05 | yaml schema decode | 5 | T04 |
| T06 | manifest and profile | 5 | T05 |
| T07 | rules model | 5 | T05 |
| T08 | expression lexer and parser | 7 | T03, T07 |
| T09 | regex binding | 2 | T08 |
| T10 | expression evaluation | 4 | T09 |
| T11 | CSV lexical layer | 9 | T02 |
| T12 | CSV field mapping | 8 | T11 |
| T13 | row conversion | 4 | T03, T12 |
| T14 | template syntax and validation | 7 | T13 |
| T15 | template rendering | 9 | T14 |
| T16 | journal model and emission | 11 | T15 |
| T17 | journal parsing and comparison | 8 | T16 |
| T18 | discovery and snapshots | 13 | T06 |
| T19 | engine | 14 | T10, T17, T18 |
| T20 | finalization | 5 | T16, T18 |
| T21 | command-line interface | 10 | T19, T20 |
| T22 | server lifecycle | 5 | T21 |
| T23 | read-only state view | 6 | T22 |
| T24 | rule editing and save | 9 | T23 |
| T25 | preview and interactive finalization | 5 | T24 |
| T26 | compatibility and determinism | 8 | T25 |
Phases #
- Foundation — T01–T03. Nothing else builds without these.
- Configuration — T04–T07.
- Matching — T08–T10.
- CSV and rows — T11–T13.
- Templates — T14, T15.
- Journal — T16, T17.
- Project — T18–T20.
- Command line — T21.
- Web interface — T22–T25.
- Cross-cutting — T26.
T11 depends only on T02, so phase 4 can run in parallel with phases 2–3. T18 depends only on T06 and can start as soon as the manifest loads.
Blocked items #
None. The two that existed are resolved: DESIGN_M1.md §11.1 (whitespace-only posting comments) and R5 (hledger 1.52.3 availability, with its URL and hash recorded in §10.3).
Sizing #
Largest tasks are T19 (engine, 14) and T18 (discovery, 13). Both are single coherent modules whose requirement IDs are individually small; neither spans a subsystem. The web interface is deliberately four tasks rather than one, so each is reviewable and carries its own status.